specializing in the production of turbines.
This complex, comprehensive order, which we carried out efficiently and successfully, included: analysis and consultation of the insulation design, dimensioning, design, prefabrication along with the delivery and assembly of shielding elements of the aluzinc sheet sheath and insulation materials on the turbine installation
- on a total area of approx. 15,000m2 - including approx. 800 complex covers (boxes) on valves and expansion joints.
This project involving about 30 people at the construction site and a dozen or so people at the central workshop in Stargard was a big challenge for us - both in technology and logistics - requiring full coordination of the activities of our departments in our company. Thanks to the commitment of a dedicated team of our employees, we were able to fully meet this task and we are proud of the final result.